Operations center progress
Posted: Dec 21, 2020
Arrowsmith SAR has outgrown its Alberni Highway’s facility shared with the Combs-Hillier’s Fire Department. Unable to expand on the current site, ASAR began discussions with Qualicum Beach and a site was selected at the airport in 2019. Over the winter and spring, we received approval of building plans and permits for the new Operation Centre. In the fall, ASAR cleared and serviced the land, and designed and built the outer shell of the new building. The project is progressing as planned with the building scheduled for lockup early in January, 2021. Work on the interior space will then start, with completion planned for summer next year.